Brief No. 030Medium Landing Ship

$269M first hull: TOTE picks Hanwha's Philadelphia yard to build a Navy Medium Landing Ship

The Oct. 30 selection is the first shipyard award under TOTE Services' $2.2 billion vessel construction manager contract for the Medium Landing Ship. It covers one ship with options for three more, and it puts a commercial manager, not the Navy, between the shipyards and the money.

Hanwha LSM award (one ship)
$269M
Options for 3 more, per TOTE [1]
TOTE VCM contract, N0002426C2421
$2.206B
Firm-fixed-price, signed July 13 [3]
Reconciliation LSM procurement
$1.804B
P.L. 119-21 sec. 20002(19), through FY2029 [5]
Reconciliation LSM advance procurement
$160M
P.L. 119-21 sec. 20002(18) [5]
Planned LSM fleet
35 ships
Up to 8 under TOTE base contract [1]

BLUF Bottom line up front

$269 million buys the first shipyard slot. TOTE Services, the commercial vessel construction manager (VCM) the Navy hired in July to run the Medium Landing Ship (LSM) program, said on Oct. 30 that it had selected Hanwha Defense USA (HDUSA) to build one LSM at Hanwha Philly Shipyard, with options for three more [1]. Construction is set to start in the fourth quarter of 2027 and TOTE expects the first vessel in 2030 [1]. For shipbuilders and their suppliers, the award is the first test of a model in which the Navy’s contract runs to a manager, and the yards compete for subcontracts on that manager’s terms.

The money

Two contracts sit on top of each other. The Navy’s piece is contract N0002426C2421, signed July 13 by Naval Sea Systems Command headquarters [3]. Federal award data list it as a firm-fixed-price definitive contract for commercial services, competed under full and open competition, with one offer received and $2.206 billion obligated at signing [3]. Its period of performance runs to Sept. 30, 2031 [3]. TOTE describes the same award as $2.2 billion “for Vessel Construction Management services for the new construction of up to eight (8) Medium Landing Ships” [2].

The Hanwha award is the second layer: one ship at $269 million, chosen through a request for proposals TOTE sent to qualified U.S. yards in July [1]. TOTE said Hanwha won “based on its competitive pricing and acceptance of TOTE Services’ subcontract terms and conditions” [1]. Neither TOTE nor the Navy has published the price of the three option ships or the subcontract’s pricing type.

Where does Medium Landing Ship money come from?

The largest LSM appropriation on the public record is in the 2025 reconciliation law. Section 20002 of Public Law 119-21 provided $1,803,941,000 “for procurement of Landing Ship Medium” and $160 million for LSM advance procurement, both available until Sept. 30, 2029 [5]. The same section paid for a second Virginia-class submarine in fiscal 2026 and two additional DDG-51 destroyers [5]. Topline Report covered the section’s unmanned surface vessel money in its MUSV brief.

The annual bills carry nothing for the ship this year. Neither the House-passed H.R. 8800 nor the Senate committee’s S. 4784 includes a Medium Landing Ship line in its fiscal 2027 Shipbuilding and Conversion, Navy table; the amphibious lines in both are the LPD Flight II and LHA Replacement [6, 7]. No public document ties the TOTE contract to a particular appropriation.

The programs

The LSM is meant to carry Marines, vehicles and supplies between islands and along coasts, chiefly in the Indo-Pacific, according to gCaptain [8]. The services plan a 35-ship fleet [1].

Three yards are in the picture. Hanwha is the first selected [1]. TOTE says it “continues productive contract discussions with Bollinger Shipyards and Fincantieri Marinette Marine, both directed shipyards under the VCM contract,” and expects both to build part of the fleet [1]. The Inquirer described the Louisiana and Wisconsin yards as already among those building the ships [9]; TOTE’s release does not announce subcontracts for either.

TOTE’s July release named its own subcontractors on the technical side: Leidos Gibbs & Cox, The McHenry Management Group, MAD Security and Damen [2].

What changes for LSM equipment suppliers?

Suppliers should expect to deal with TOTE as well as the yards. The firm says its job includes standardizing configuration across the fleet and using block buys to secure favorable pricing across three domestic builders [1]. In July it said it would handle supplier engagement alongside shipyard selection and construction planning [2].

What the award means for Hanwha Philly Shipyard

For the Philadelphia yard, this is the first Navy hull. The Inquirer reported it will be the first Navy vessel built in Philadelphia since the Philadelphia Naval Shipyard closed in 1995 [9]. Hanwha bought the yard in December 2024 [8], and gCaptain reported that HDUSA announced the same week that it is taking a controlling stake in the shipyard [8].

The yard already works under TOTE. It built the National Security Multi-Mission Vessels, training ships TOTE manages as VCM for the Maritime Administration; four of five have been delivered and the fifth, Golden State, is expected in 2027 [1, 8]. Hanwha told the Inquirer it has spent $350 million on the yard since 2024 and plans another $400 million for a dry dock, a training center and more production sites [9]. The yard employs about 2,300 people and Hanwha says it wants 4,000 or more [9].

“Since early this year, HDUSA personnel have been in Philadelphia working to ensure the shipyard is ready for naval work,” said Tim Glinatsis, HDUSA’s senior vice president of program management [1].

The politics: how the VCM model got into law

Congress wrote the arrangement into statute. Section 129 of the fiscal 2026 NDAA, Public Law 119-60, directs the Navy secretary, after the award of the LSM lead ship, to “seek to enter into an agreement with an appropriate vessel construction manager” to contract for “not more than 8 additional landing ships” [4]. Those ships must be nondevelopmental and use the lead ship’s design or one derived from it [4]. The same section points the Navy at VCMs for light replenishment oilers (TAO-L) and allows them for auxiliary and support vessels [4]. TOTE’s release does not say how the Hanwha hull relates to the lead ship the statute describes.

A separate provision, Section 127, lets the Navy contract for up to 15 Medium Landing Ships if the secretary certifies 30 days ahead that the deal saves money against annual contracts and that the design is stable [4]. That authority ends Sept. 30, 2029 [4].

The fiscal 2027 bills would push the model further:

  • Senate Section 1013 would change “not more than” to “not fewer than” in the eight-ship VCM clause, turning a ceiling into a floor, and would extend the optional VCM authority to unmanned vessels and other ships outside the battle force [6].
  • Senate Section 123 would require the Navy, if it buys cable laying and repair ships, to seek a VCM agreement and use commercial designs [6].
  • House Section 3665 would order an assessment of commercial shipbuilding practices, naming “the vessel construction manager model used to construct the National Security Multi Mission Vessel Program” as one to evaluate [7].

None of the three is law. All depend on a House-Senate conference on H.R. 8800 and S. 4784.

TOTE frames the award as proof of speed. “This award shows the speed at which the VCM model can move from RFP to contract,” said Jeff Dixon, TOTE’s president [1]. He credited the Navy’s Portfolio Acquisition Executive for Maritime (PAE Maritime) for “removing longstanding barriers to execution” [1]. The Inquirer reported that the TOTE system is designed to hold off all but the most necessary changes once building begins, an answer to change orders that Navy officials have blamed for delays and overruns [9].

Next milestone: when do the other LSM yards get contracts?

TOTE has not given a date for awards to Bollinger or Fincantieri Marinette [1]. The firm dates on the record are the ones it set itself: a construction start in the fourth quarter of 2027 at Philadelphia and a first delivery in 2030 [1]. The Section 127 contract authority and the reconciliation money both run out on Sept. 30, 2029 [4, 5]. Whether the three Hanwha options are exercised, and at what price, has not been disclosed.

Contract Tracker

2 awards referenced in this brief

DateContractorValueProgramTypeAgencySrc
Hanwha Defense USA (Hanwha Philly Shipyard)$269MMedium Landing Ship, one hull plus three optionsShipyard subcontract under VCMNavy (through TOTE Services)[1]
TOTE Services, LLC$2.206BMedium Landing Ship vessel construction management, up to 8 shipsFirm-fixed-price definitive contractNavy (NAVSEA / PAE Maritime)[3]

Readout

Questions on this brief, answered from the cited record

Who is building the Navy's Medium Landing Ship in Philadelphia?
Hanwha Defense USA, at Hanwha Philly Shipyard. TOTE Services, the program's vessel construction manager, selected the company on Oct. 30, 2026 for one ship valued at $269 million, with options for three more [1].
When will construction of the first Medium Landing Ship in Philadelphia start?
TOTE Services says the build positions allow construction to start in the fourth quarter of 2027, with its first vessel expected in 2030 [1]. A Hanwha spokesperson told the Inquirer work would begin by 2028 [9].
Does the Navy contract directly with the shipyards on the Medium Landing Ship?
No. TOTE Services holds the prime contract with the Navy's PAE Maritime and awards and manages the shipyard subcontracts itself [2]. The Navy's award to TOTE is a $2.206 billion firm-fixed-price contract signed July 13, 2026 [3].
How many Medium Landing Ships can TOTE Services build under its contract?
Up to eight under the base contract, toward a planned fleet of 35 [1, 2]. Current law caps the vessel construction manager's share at not more than eight additional ships; the Senate's FY2027 bill would change that to not fewer than eight [4, 6].
Are Bollinger and Fincantieri building Medium Landing Ships?
TOTE Services calls Bollinger Shipyards and Fincantieri Marinette Marine directed shipyards under its contract and says it is in contract discussions with both [1]. Neither had a TOTE subcontract announced as of Oct. 30 [1].

Sources

  1. TOTE Services Identifies Hanwha Defense USA for Medium Landing Ship Construction; Additional Shipyard Selections PlannedTOTE Services, October 30, 2026
  2. TOTE Services Awarded VCM Contract to Oversee Medium Landing Ship Construction ProgramTOTE Services, July 13, 2026
  3. Contract N0002426C2421, TOTE Services, LLC: award record (definitive contract, NAVSEA)U.S. Department of the Navy, July 13, 2026
  4. Public Law 119-60, National Defense Authorization Act for Fiscal Year 2026, sections 127 and 129U.S. Congress, December 18, 2025
  5. Public Law 119-21 (H.R. 1), section 20002U.S. Congress, July 4, 2025
  6. S. 4784, National Defense Authorization Act for Fiscal Year 2027 (Reported in Senate), sections 123, 1013 and 4101U.S. Senate Committee on Armed Services, June 15, 2026
  7. H.R. 8800, National Defense Authorization Act for Fiscal Year 2027 (Engrossed in House), sections 3665 and 4101U.S. House of Representatives, July 22, 2026
  8. Hanwha Philly Shipyard Wins $269 Million U.S. Navy Landing Ship ContractgCaptain, October 30, 2026
  9. Navy shipbuilding returns to Philly in $269 million deal for a Marine landing shipThe Philadelphia Inquirer, October 30, 2026

Note on sourcing

The $269 million value, the option count, the fourth-quarter 2027 construction start and the 2030 first delivery are TOTE Services' figures. The Navy had not issued its own announcement of the Hanwha selection as of publication, and the subcontract's pricing type and option values have not been published. The Philadelphia Inquirer reported a first delivery 'by late 2029' for the program, a year earlier than TOTE's date for its first vessel; this brief uses TOTE's date. Hanwha's investment and employment figures are the company's, as reported by the Inquirer. No public document cited here ties the TOTE contract to a specific appropriation. The Senate and House provisions described are from S. 4784 as reported and H.R. 8800 as passed by the House, which had not been reconciled or enacted as of publication.