Brief No. 033Undergraduate Jet Training System
$80.6M FY2027 request, one known major bidder: Navy's T-45 replacement trainer enters source selection
Proposals for the Undergraduate Jet Training System closed Oct. 30 with Sierra Nevada out and Textron's M-346N the only established design known to have bid. The Navy now targets an award in the fourth quarter of fiscal 2027, while its development line waits on full-year money.
BLUF Bottom line up front
In 2025 the Navy’s Undergraduate Jet Training System (UJTS) drew four industry teams [4]. When proposals closed on Oct. 30, 2026, the only established design known to be in the competition was Textron Aviation Defense’s M-346N, after Sierra Nevada Corporation (SNC) said it would not bid [1, 2]. The program office says it is in source selection and intends to award in the fourth quarter of fiscal 2027, between July and September [1]. For contractors and suppliers, the replacement for the T-45 Goshawk is now a sole-known-bidder competition with a development line that, under the stopgap, still runs at last year’s rate [5, 8].
The money
UJTS development is funded in the Navy research, development, test and evaluation (RDT&E) program element 0603208N, Training System Aircraft [5]. The FY2027 request is $80.617 million [5, 6]. Both the House-passed H.R. 8800 and the Senate Armed Services Committee’s S. 4784 authorize exactly that amount, with no adjustment in either funding table [6, 7].
The FY2026 enacted level for the same line was $30.2 million, according to budget data compiled by HigherGov [5]. By this brief’s arithmetic, the request is about $50.4 million higher, more than two and a half times the FY2026 figure. The Navy’s budget materials, as summarized by HigherGov, say the FY2027 money supports continued source selection, Milestone B approval and the award of an engineering and manufacturing development (EMD) contract [5]. The line is not UJTS alone: it also pays for upgrades to the T-45, T-6, T-44, TH-73A and T-54, and the FY2027 request moves away from T-45 physiological-episode work as the GGU-25 flight test winds down in September 2026 [5].
Aviation Week put the initial award costs at $52.8 million in FY2027 and $181 million in FY2028, The War Zone reported [2]. The War Zone and a Breaking Defense opinion piece both report a ceiling raised earlier this year from about $1.8 billion to $2.7 billion; the opinion piece says the change came in May and describes it as the EMD price ceiling [2, 3]. Halldale Group has described the overall program at more than $10 billion for up to 216 airframes [4].
The existing fleet is funded separately. The FY2027 request for T-45 Series modifications in Aircraft Procurement, Navy is $191.1 million, and both chambers authorize it as requested [6, 7].
The Pentagon is operating under the continuing resolution in P.L. 119-103 until Dec. 11, 2026 [8]. Section 102 bars new production, production-rate increases, and any program element or project that had no funds in fiscal 2026 [8]. PE 0603208N had FY2026 money, so the constraint on UJTS is the rate, not the new-start bar, a point covered in this site’s brief on the Dec. 11 deadline. With the award not planned until late fiscal 2027, the request matters more for when it is appropriated than for this quarter [1, 5].
The programs: who is left in the Navy jet trainer competition?
The field shrank over seven months:
- Lockheed Martin and KAI withdrew the TF-50N, a navalized T-50, on April 23, 2026 [4]. The Breaking Defense opinion piece says Lockheed cited U.S. content requirements [3].
- Boeing and Saab withdrew the T-7A-based offer in early June [4]. Boeing said the design needed further development, including engine qualification, according to The War Zone and the opinion piece [2, 3].
- Northrop Grumman left SNC’s team in September [1, 2].
- SNC said on Nov. 3 that it “could not responsibly bid the UJTS” program “under the current contract structure” [1]. Its Freedom Jet was the only clean-sheet design in the race [2].
Textron confirmed it submitted the M-346N, a version of the Leonardo M-346 powered by Honeywell F124 turbofans [2]. Stavatti Aerospace said on Oct. 30 that it had also submitted a bid [1]. Whether anyone else proposed is not public [2].
The Navy wants 216 new aircraft to replace just under 200 T-45s [2]. The final request for proposals came out March 26, 2026, with offers first due June 29 [4]. The opinion piece says the deadline moved to Sept. 9 and then to Oct. 30 [3]. The award target has moved with it: March 2027 at the outset, and now the fourth quarter of fiscal 2027 [1, 2].
The requirements changed too. The March RFP does not require the trainer to land on a carrier [1, 4]. It must instead “support FCLP to wave off,” meaning students fly field carrier landing practice approaches only to the wave-off point rather than through touchdown [1, 4]. The War Zone called the change controversial [2]. Halldale Group noted that the engine requirements still call for carrier-environment durability [4].
According to the HigherGov compilation of Navy budget data, the program plans a preliminary design review in FY2028, a critical design review in FY2029, developmental testing starting in FY2030, and Milestone C with low-rate initial production in FY2031 [5]. The Navy has said aircraft, engine and component obsolescence will sharply cut T-45 availability by 2035, according to the same compilation [5]. The opinion piece says a service life extension keeps about 145 T-45s flying, that NAVAIR plans to keep the Goshawk in service through 2040, and that first production deliveries are not expected until 2032 [3].
Halldale Group describes UJTS as an integrated training capability covering aircraft, simulators and digital training tools [4]. For suppliers, that means the award covers more than an airframe, and with one established offeror known, the open question is whose team holds that work [1, 4].
The politics
Congress has not moved the money. Neither the House nor the Senate bill changes the Training System Aircraft request [6, 7]. H.R. 8800 does name the T-45 once, in Section 766, as an example of a trainer jet in a study of the long-term effects of military flight operations on aviators [6]. Neither bill text addresses the UJTS competition itself [6, 7].
The industry positions are on the record. SNC said: “We do remain committed to naval jet training and stand ready to re-engage if the approach is revisited” [1]. A Textron spokesperson said the company is “ready to support the U.S. Navy and its future training needs” [1].
The argument over what the Navy should do now is also public. Robbin Laird, writing in Breaking Defense, argues the program is the main test of the Pentagon’s acquisition reforms and that the Navy should not reopen the competition by default, should evaluate the remaining bid rigorously and should hold or beat the award date [3]. SNC’s statement points the other way: it asks the Navy to revisit the contract approach, which would mean changing the terms that drove it out [1]. The War Zone’s account adds that SNC built the Freedom Jet to keep the carrier-qualification and field-landing capability the RFP dropped [2]. The Navy has not published the contract structure SNC objected to, and no Navy statement in the record this brief draws on responds to it [1, 2].
Next milestone: when could the UJTS contract be signed?
The first dated step is not the Navy’s. The CR expires Dec. 11, 2026, and full-year defense appropriations would set the FY2027 level for PE 0603208N [8]. The final FY2027 NDAA also has to be reconciled from H.R. 8800 and S. 4784 [6, 7].
Then source selection. The program office’s target is a contract signed between July and September 2027, alongside the Milestone B decision the budget request describes [1, 5]. A preliminary design review would follow in FY2028 [5].
Two things could move the date. One is the Navy deciding to reopen or restructure the competition, which SNC has invited and the Breaking Defense opinion piece argues against [1, 3]. The other is the evaluation of a field where the only established offeror sets the price. What the “current contract structure” requires of the winner, in pricing type, risk and options, is the term no public document has yet described [1].
Readout
Questions on this brief, answered from the cited record
- Who is still competing to replace the Navy's T-45 Goshawk trainer?
- Textron Aviation Defense, with the Leonardo-derived M-346N, is the only established design known to have bid [1, 2]. Stavatti Aerospace said it also submitted a proposal on Oct. 30; Lockheed Martin, Boeing and Sierra Nevada all left the competition [1, 3].
- When will the Navy award the UJTS contract?
- The UJTS program office says it intends to award in the fourth quarter of fiscal 2027, which runs July through September 2027 [1, 2]. Earlier plans had targeted March 2027 [2, 4].
- Why did Sierra Nevada drop out of the Navy jet trainer competition?
- SNC said it could not responsibly bid under the current contract structure, and that it would re-engage if the approach is revisited [1]. It did not say publicly which terms it objected to [1, 2].
- Does the new Navy trainer have to land on an aircraft carrier?
- No. The March 2026 request for proposals drops carrier landings and only requires the aircraft to fly field carrier landing practice approaches through to a wave-off [1, 4].
- How much is the Navy requesting for UJTS in fiscal 2027?
- The development money sits in the Training System Aircraft line, PE 0603208N, which carries an $80.6 million FY2027 request that both the House and Senate NDAA bills authorize unchanged [5, 6, 7]. That line also funds upgrades to other trainers [5].
Sources
- SNC pulls out of Navy's trainer jet competition, leaving Textron likely winnerBreaking Defense, November 3, 2026
- The Beechcraft M-346N Is The Only Known Aircraft Left In The Navy's Jet Trainer CompetitionThe War Zone, November 4, 2026
- The Navy's trainer is now the biggest test of the Pentagon's acquisition reform efforts (opinion, Robbin Laird)Breaking Defense, November 6, 2026
- US Navy's Undergraduate Jet Training System: Competition Narrows as Training Requirements EvolveHalldale Group, July 7, 2026
- Training System Aircraft, PE 0603208N (RDT&E, Navy): FY2027 budget detailHigherGov, accessed 2026-11-08
- H.R. 8800, National Defense Authorization Act for Fiscal Year 2027 (Engrossed in House), sections 4101 and 4201U.S. House of Representatives, July 22, 2026
- S. 4784, National Defense Authorization Act for Fiscal Year 2027 (Reported in Senate), sections 4101 and 4201U.S. Senate Committee on Armed Services, June 15, 2026
- Continuing Appropriations and Extensions Act, 2027 (Public Law 119-103), compilationU.S. Congress, September 22, 2026
Note on sourcing
The Navy has not published a list of offerors, so the field described here rests on company statements reported by Breaking Defense and The War Zone; whether any other bid was submitted is not public. The roughly $2.7 billion ceiling, up from about $1.8 billion, is as reported by The War Zone and in a Breaking Defense opinion piece, which describe it differently (a total cost ceiling and an engineering and manufacturing development price ceiling, respectively); no Navy document in the record this brief draws on states it. The $52.8 million and $181 million award-cost figures are Aviation Week's, as cited by The War Zone. The program-element description, the FY2026 enacted figure and the milestone schedule are as compiled by HigherGov from Navy FY2027 budget data, not drawn from the Navy's justification book directly. The fleet figures (about 145 T-45s under a service life extension, service through 2040, first production deliveries in 2032) appear in the Breaking Defense opinion piece and have not been confirmed against a NAVAIR statement. The comparison of the FY2027 request with the FY2026 enacted level is this brief's arithmetic. The terms of the contract structure Sierra Nevada objected to have not been made public.